CPECN

Sigma Lithium begins work on dense media separation plant

Adam Dras   

Announcements News

Vancouver, B.C.’s Sigma Lithium Corporation, a producer of electric vehicle batteries with high-purity lithium, has started construction of its greentech dense media separation production plant at its Grota do Cirilo project in Brazil.
The company stated that is has also secured 38 critical long lead items required for the project and has begun to order them from respective suppliers, placing deposits to secure manufacturing timetables. Prices and FEL-3 quotes for these long lead items have been in line with the FEL-2 capex estimates in the feasibility study included in the company’s most recently filed technical report.
Completion of this stage of the construction civil works is expected within three months, when the Brazilian sub-construction firm of Promon Engenharia Ltda. is expected to complete earthworks and the concrete plant drainage channels. This stage follows the  last month’s mobilization of approximately 180 workers and construction equipment to the site.
“This is a tremendous milestone for Sigma Lithium, now initiating the construction of the production plant, following the successful completion of mobilization and the front-end engineering and design. As a result, we have been able to quote FEL-3 Capex in line with our FEL-2 estimates in our feasibility study. Our team has worked tirelessly this year on several fronts on detailed engineering and pre-construction with the environmental focus that has been a hallmark of Sigma,” Calvyn Gardner, Sigma co-CEO and lead engineer on the ground at construction site, explained in a statement.


Print this page

Advertisement

Stories continue below